We planned and executed a vibroseis 3D seismic survey in the Cooper Basin using low impact, high production techniques.


Project Summary

We planned and executed a vibroseis 3D seismic survey in the Cooper Basin using low impact, high production techniques.

262 km² 3D Seismic Survey in the Cooper Basin, South Australia. 

18,298 Receiver Points, 18,256 Source Points.

Timeframe - Planning 29 days, Delivery 42 days. 

Seismic contractor - Terrex Seismic

Recording System - Nodal - Smart Solo IGU-16

Source Type - Vibroseis - 4 fleets of 1 x AHV-IV PL364 62,000lb

Service categories

  • Project Planning
  • Environmental Planning
  • Regulatory Interface
  • Project Delivery