Projects

Land seismic project experience

Selected land seismic programs managed across Australia and New Zealand, covering a range of survey types, terrains and regulatory environments.

White vibroseis survey trucks with a seismic point marker in the field, Eromanga Basin, Queensland
Eromanga Basin3D vibroseis · Queensland
Client-side planning and project management for a large-scale 3D vibroseis program across sensitive environments in the Eromanga Basin.
Project Snapshot
LocationEromanga Basin, Queensland
ResourceGeo RoleClient-side Project Manager
Client TypeExplorer
Year2023
Survey Type3D Seismic
Receiver PointsApprox. 25,000
Source PointsApprox. 12,000
Source TypeVibroseis
Recording SystemSercel 428XL
Planning Timeframe6 Months
Field duration8 Weeks
Engaged for
Project Management Land Access Environmental Management Regulatory Approvals Cultural Heritage Management Field Supervision
8-week field program completed on schedule, with all regulatory and cultural heritage clearances secured ahead of mobilisation.
Convoy of vibroseis units raising dust in desert terrain, Cooper Basin, South Australia
Cooper Basin3D vibroseis · South Australia
Client-side project management for a large-scale 3D seismic acquisition, balancing high production rates with stringent HSE requirements.
Project Snapshot
LocationCooper Basin, South Australia
ResourceGeo RoleClient-side Project Manager
Client TypeExplorer
Year2024
Survey Type3D Seismic
Receiver PointsApprox. 35,000
Source PointsApprox. 18,000
Source TypeVibroseis
Recording SystemSmart Solo IGU-16
Planning Timeframe2 Months
Field duration12 Weeks
Engaged for
Project Management Land Access Environmental Management Regulatory Approvals Field Supervision
12-week high-production acquisition program completed on schedule, with HSE standards maintained under ResourceGeo's client-side management.
Survey vehicles in a dry agricultural paddock, Otway Basin, South Australia
Otway Basin3D vibroseis · South Australia
Agricultural land access and regulatory constraints managed across South Australia for a 3D seismic survey.
Project Snapshot
LocationOtway Basin, South Australia
ResourceGeo RoleField Operations Manager
Client TypeOperator
Year2023
Survey Type3D Seismic
Receiver PointsApprox. 3,300
Source PointsApprox. 5,900
Source TypeVibroseis
Recording SystemSmart Solo IGU-16
Planning Timeframe4 Months
Field duration2 Weeks
Engaged for
Project Management Regulatory Approvals Field Supervision
South Australian approvals secured within the 4-month planning window, supporting a 2-week field program.
Aerial view of two vibroseis units on an access track, Bowen Basin, Queensland
Bowen Basin2D vibroseis · Queensland
Client-side management of a 2D seismic acquisition program across complex terrain, addressing significant regulatory and environmental constraints.
Project Snapshot
LocationBowen Basin, Queensland
ResourceGeo RoleClient-side Project Manager
Client TypeOperator
Year2025
Survey Type2D Seismic
Receiver PointsApprox. 5,000
Source PointsApprox. 2,500
Source TypeVibroseis
Recording SystemSmart Solo IGU-16 & AllSeis-1C
Planning Timeframe5 Months
Field duration4 Weeks
Engaged for
Project Management Field Supervision Pre & Post-Survey Drone Imagery
4-week field program completed on schedule, with drone-based condition records supporting land access close-out.
Arid red-soil landscape with a survey vehicle, Amadeus Basin, Northern Territory
Amadeus Basin2D weight-drop · Northern Territory
Complex remote operations and extensive stakeholder engagement managed for a weight-drop 2D seismic program.
Project Snapshot
LocationAmadeus Basin, Northern Territory
ResourceGeo RoleClient-side Project Manager
Client TypeExplorer
Year2024
Survey Type2D Seismic
Receiver PointsApprox. 8,000
Source PointsApprox. 4,000
Source TypeWeight Drop
Recording SystemStryde
Planning Timeframe8 Months
Field duration4 Weeks
Engaged for
Project Management Field Supervision Pre & Post-Survey Drone Imagery
4-week field program completed in a remote environment, with stakeholder commitments tracked through to close-out.
Field surveyor in green farmland, Taranaki Basin, New Zealand
Taranaki Basin2D dynamite · New Zealand
Complex permitting and challenging operational terrain managed for a dynamite 2D seismic program in New Zealand.
Project Snapshot
LocationTaranaki Basin, New Zealand
ResourceGeo RoleSeismic Project Manager (prior to founding ResourceGeo)
Client TypeOperator
Year2019
Survey Type2D Seismic
Receiver PointsApprox. 3,500
Source PointsApprox. 1,500
Source TypeDynamite / Heli-portable
Recording SystemFairfield Z-Land
Planning Timeframe4 Months
Field duration5 Weeks
Engaged for
Project Management Field Management
5-week field program completed under the direct field management of ResourceGeo's Principal, prior to founding ResourceGeo.